Completion of pipeline diversion works near Leicester Lane, Cubbington
Work item: HS2-EW-UT-Ph1-Ar-No-N1-Prog-works-27-04/12/2021 – 2
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Cubbington
- Contractor
- Cadent Gas
- Type of works
- Utility works / surveys
- Estimated Start Date
- 28/09/2021
- Estimated End Date
- 28/09/2021
What we are doing
We have now finished moving the pipe on land between Leicester Lane and Coventry Road, and have successfully carried out routine testing on the relocated pipeline. We are currently carrying out work to replace topsoil and vegetation that we had to remove to carry out the diversion.
All Cadent work at this site is now complete. We would like to thank local people for their continued patience throughout the duration of our work.
The site accesses off Leicester Lane and the temporary works compound that Cadent has been using will remain in place for other HS2 works.