Continued single lane closures on and around Northway Island

Work item: HS2-EW-LM-Ph1-Ar-No-N1-OTH-2-15/12/2020

Work Item Summary

Project Phase
Phase 1
Region
Solihull, West Midlands
Location
Bickenhill
Contractor
LM JV
Type of works
Traffic management
Estimated Start Date
21/12/2020
Estimated End Date
26/04/2021

Work item details

We are remodelling and improving sections of the existing road network in the area, and constructing new routes on HS2 land, which will connect to four new highway bridges. These road improvements will ensure that when the future HS2 Interchange Station is operational, the local road network is fit for purpose.

This is an ongoing programme of works, which commenced in March 2020 in the Interchange area.

From Monday 4 January 2021, single lane closures will be installed on and around Northway Island until Monday 26 April 2021. Our working hours will be 7am to 6pm, but some traffic measures will remain in place 24-hours. We’ll work Monday to Friday, however we may extend our works into the weekend if required. Temporary traffic lights will continue to be used intermittently along the A452 during our work.

You will still be able to travel along all routes in both directions.

Download information relating to these works

We'd like your feedback

Please help us improve how we keep you informed about how we're delivering the railway by giving us feedback on your experience.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]