Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-10-05/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 24/05/2021
- Estimated End Date
- 30/07/2021
What we are doing
This newsletter is a summary of current and upcoming works at the Willesden Euroterminal site from May to July this year.