Demolition works to One Euston Square and Grant Thornton House Buildings

Work item: HS2-EW-MD-Ph1-Eu-St-S3-Site-11-12/09/2020

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden, Euston station
Contractor
Mace Dragados JV
Type of works
Demolition works
Estimated Start Date
05/01/2021
Estimated End Date
29/07/2022

Work item details

In advance of the proposed HS2 station Mace Dragados will continue and complete the demolition works to One Euston Square and Grant Thornton buildings, west side of Euston Station.

These works will continue until July 2022. Most of the construction works are planned to take place during core working hours only. However, it may be necessary to undertake some works during the weekend and at night. This is so that we can reduce the impact on the public and commuters at Euston Station.

Download information relating to these works

We'd like your feedback

Please help us improve how we keep you informed about how we're delivering the railway by giving us feedback on your experience.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]