Gas connection works on Varndell Street

Work item: HS2-EW-SCS-Ph1-Eu-St-S3-UT-49-09/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden, Hampstead Road, Harrington Street, Stanhope Street
Contractor
CS JV
Type of works
Road closure, Utility works / surveys
Estimated Start Date
27/09/2021
Estimated End Date
18/11/2021

What we are doing

Varndell Street Gas Works – 27 September to 17 November 2021

  • CSJV will carry out gas connection works on Varndell Street between the junctions at Harrington Street and
    Hampstead Road.
  • These works will be completed in three phases:
    • Phase 1: 27 September to 8 October, road closed between Hampstead Road and Harrington Street for excavation works
    • Phase 2: 11 to 15 October, road closure will include closure of the junction of Varndell Street and Harrington Street
    • Phase 3: 18 October to 12 November, road remain closed for gas pipe installation and connection works.
    • Phase 4: 14 November to 17 November, Closure on Varndell street & and the lights on Hampstead road for carriageway remedial works, no footways will be closed
  • Junction with Hampstead Road will be closed throughout the works
  • Access to  Regents Park Estate will be maintained via Robert Street and Stanhope Street.
  • Footways will remain open with pedestrian and traffic diversion signs will be in place.
  • Refuse collection services in each phase will be maintained at all times.

Please see notification of works below.