View In Your Area map
Ground investigation south of Hale Road
Work item: HS2-EW-BBV-Ph2b-Man-Prog-works-7-08/03/2021
Work Item Summary
- Project Phase
- Phase 2b
- Region
- Manchester
- Location
- Hale Barnes
- Worksite Name
- Hale Road
- Contractor
- Balfour Beatty
- Type of works
- Ground investigations
- Estimated Start Date
- 17/08/2021
- Estimated End Date
- 08/10/2021
What we are doing
Ground investigations works are being carried out to help us better understand the ground conditions along the route to inform the detailed design of the railway.
The ground investigation techniques that will be used on this project will primarily include the drilling of boreholes, trial pits and cone penetration tests.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]