Ground Investigation surveys – Ufton
Work item: HS2-EW-LM-Ph1-Ar-No-N1-Prog-works-12-06/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Ufton
- Contractor
- LM JV
- Estimated Start Date
- 12/07/2021
- Estimated End Date
- 25/07/2021
What we are doing
LM will be carrying out ground investigation surveys, to determine utility locations, along the A425 Southam Road in Ufton on Monday 12 July to Sunday 25 July 2021. In order to carry out these works safely, three-way traffic lights with a lane closure will be erected daily on the A425 Southam Road and White Hart Lane between 7:00am to 6:00pm. Working hours will be between 8:00am to 6:00pm.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]