HS2 Notification: Notice of Thames Water works – The Green

Work item: HS2-MW-TW-Ph1-Ar-So-S1-Prog-works-3-10/05/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Ruislip
Worksite Name
West Ruislip
Contractor
Thames Water
Type of works
Utility works / surveys
Estimated Start Date
18/10/2021
Estimated End Date
31/10/2021

What we are doing

Thames Water update
As part of our work, to divert our sewer to make way for the new HS2 railway, we will be starting our main work on the Ruislip Golf Course w/c Monday 18 October.

The Golf Course main works
Our work will first involve us creating a new small section of temporary access track branching off the existing (unclassified) construction access to Ruislip Public Golf Course.

Once we have set up our work site, we will start tunnelling under the railway line. This work will be carried out under permitted development.
We will write to you again when we cross the railway line and enter the southern section of our work.

Enabling work by The Green

We plan to start enabling works on Monday 18 October, subject to planning permission being granted by London Borough of Hillingdon on Thursday 14 October, with no planning conditions that would restrict work starting on that date. We will write to you again about our work programme if we get planning permission.

Getting in touch
For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: BB 972617.
Phone: 0800 316 9800 (our lines are always open) Email: [email protected]

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]