Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Euston station
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 15/06/2021
- Estimated End Date
- 31/07/2021
What we are doing
UKPN run the electricity network delivering power to your area and are due to start work soon on a project to upgrade equipment to ensure reliable power supplies for local homes and businesses. The work, in partnership with our contractor Modus Utilities, is needed to provide a new electricity connection for the HS2 Project.
Work is due to start on 15th of June 2021 with planned working hours of Monday to Friday 8am to 5pm. There may be times when weekend working is required however we will minimize these shifts where possible. We expect to complete these works by the end of July 2021. During this period, works will be carried out within the carriageway/footway of Cardington Street.
Download information relating to these works