Skip to main page content
View route map

Installation of tower crane Curzon St station

Work item: HS2-BCZ – SCP-26-2255

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Curzon Street
Contractor
Mace Dragados JV
Type of works
Installation of tower crane
Estimated Start Date
10/07/2026
Estimated End Date
12/07/2026

What we are doing

Location
Curzon Street

Duration
Friday 10th July – Sunday 12th July.

Contingency date: Saturday 17 July – Monday 20th July.

What we are doing
Installation of the third of four large tower cranes on site.

What to expect
We will put the tower crane together on site using a mobile crane. HGVs will deliver the components of the crane during normal
working hours. They will arrive on site on Friday, and we will assemble over the weekend, including Sunday (8am – 6pm). Once we complete the assembly of the tower crane, we will dismantle and remove the mobile crane from site.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]