Work Item Summary
- Project Phase
- Phase 1
- Region
- Birmingham
- Location
- Curzon Street
- Contractor
- Mace Dragados JV
- Type of works
- Installation of tower crane
- Estimated Start Date
- 10/07/2026
- Estimated End Date
- 12/07/2026
What we are doing
Location
Curzon Street
Duration
Friday 10th July – Sunday 12th July.
Contingency date: Saturday 17 July – Monday 20th July.
What we are doing
Installation of the third of four large tower cranes on site.
What to expect
We will put the tower crane together on site using a mobile crane. HGVs will deliver the components of the crane during normal
working hours. They will arrive on site on Friday, and we will assemble over the weekend, including Sunday (8am – 6pm). Once we complete the assembly of the tower crane, we will dismantle and remove the mobile crane from site.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.