Main site activities in the Colne Valley Viaduct area

Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-27-09/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Colne Valley
Contractor
SCS JV
Type of works
Earth works, Excavation works, Piling
Estimated Start Date
01/09/2021
Estimated End Date
31/12/2021

Work item details

Will are currently carrying out enabling earthworks and piling activities in preparation for construction of the Colne Valley Viaduct that will cross the Colne Valley and a number of its lakes.

We produce maps showing key site activities in the Colne Valley area, view details via the pdf document below:

These maps will be updated on a weekly basis.

Download information relating to these works

We'd like your feedback

Please help us improve how we keep you informed about how we're delivering the railway by giving us feedback on your experience.

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]