Main site activities in the West Ruislip and Golf Course area

Work item: HS2-MW-Ph1-Ar-So-S2-Prog-works-30-09/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
West Ruislip
Worksite Name
West Ruislip
Contractor
SCS JV
Type of works
Earth works, Utility works / surveys, Worksite / compound set-up
Estimated Start Date
01/09/2021
Estimated End Date
31/12/2026

What we are doing

24/7 works are ongoing until 30 November 2026 within the Northolt Tunnel. We are working within the tunnel to build the emergency and maintenance walkways and continuing the fit out of our cross passages, which connect the parallel running tunnels.

Along the northern side of the Chiltern line, we are installing concrete noise barrier panels and drainage systems. The noise barrier installation will continue into 2027. We have also begun piling works, ahead of diverting the Ickenham Stream, ongoing until December 2026.

Works to construct the headhouse and porous portal are ongoing until January 2028.

In the golf course area, we will maintain the newly constructed wildlife habitat; carry out ongoing maintenance works, which will include vegetation clearance and tree pruning; maintain access to the golf course for the public via the approved footpaths; and maintain the diverted section of the U44 footpath.

We produce maps showing key site activities in the West Ruislip area, view details via the pdf document below.

These maps will be updated on a weekly basis.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]