Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Primrose Hill Tunnels
- Contractor
- Network Rail (Euston)
- Type of works
- Railway systems
- Estimated Start Date
- 20/02/2021
- Estimated End Date
- 30/12/2022
What we are doing
Network Rail are improving the existing operational railway and preparing for HS2 to be constructed. This work is vital to provide a safe, reliable and efficient railway.
Network Rail will be replacing worn rail and associated processes inside Primrose Hill Tunnel from 17 – 18 December and
24 – 25 December.
More details on the specific dates, locations and types of work are included on the letters below.
If you have any queries about Network Rail work, please contact the Network Rail 24-hour helpline on 03457 11 41 41 or email [email protected]. (Please note, this email address is only monitored during normal office hours.)