Network Rail works at Camden Canal Bridge

Work item: Network Rail

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden, Regents Park Road
Contractor
Network Rail (Euston)
Type of works
Railway systems
Estimated Start Date
24/12/2022
Estimated End Date
30/12/2022

What we are doing

Network Rail are improving the existing operational railway in your area. This work is vital to provide a safe, reliable and efficient railway.

In order to keep staff safe, Network Rail needs to carry out work at times that cause the least disruption to train services and passengers. This often means carrying out work during weeknights and weekends.

From 24 to 29 December works will be carried out at Camden Canal Bridge including removal and replacement of railway infrastructure and bridge over Regents Canal during weekdays, weekends and night-time.

If you have any queries about Network Rail work, please contact the Network Rail 24-hour helpline on 03457 11 41 41 or email [email protected]. (Please note, this email address is only monitored during normal office hours.)

More details of above works please refer to Area B in the pre-notification below.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]