Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Waddesdon
- Worksite Name
- Blackgrove Road
- Contractor
- EKFB JV
- Type of works
- Lane closure
- Estimated Start Date
- 27/04/2026
- Estimated End Date
- 20/05/2026
What we are doing
We will be completing general verge works, creating a new maintenance access point and completing a water utility connection.
Location
Blackgrove Road, Waddesdon.
Duration
We would like to update you that these works have been extended beyond Friday 8 May.
18 Days, Monday 27 April to Wednesday 20 May, excluding weekends.
What to expect
Lane closure with 2-way temporary traffic lights, Monday to Friday, 8.30am to 5.30pm.
The traffic management will be removed over the weekend.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]