Notice of construction activities in Quainton
Work item: HS2-EW-FUS-Ph1-Ar-Ce-C2-Prog-works-11-13/07/2020
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Quainton
- Contractor
- Fusion JV
- Type of works
- Archaeology, Worksite / compound set-up
- Estimated Start Date
- 03/08/2020
- Estimated End Date
- 31/05/2021
What we are doing
Before the main construction works for the railway begins, we need to undertake a number of activities:
- Construction of a compound north of Station Road
- Construction of an access road from the north of Station Road to the west of Greatmoor sidings, including culvert crossings of existing water courses including a temporary bridge across the River Ray
- Construction of public highway crossings where the access road crosses the existing highway
- Survey and investigation works on Station Road and to the junction with the A41ahead of highway improvement works