Notice of culvert surveys at Breakspear Road South and Harvil Road – Showing Breakspear Road South location
Work item: HS2-EW-SCS-Ph1-Ar-So-S2- Prog- works-3-02/07/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Breakspear Road South, Harvil Road
- Contractor
- CS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 12/07/2021
- Estimated End Date
- 30/07/2021
What we are doing
What we are doing
From 12 to 30 July 2021, we will be carrying out overnight surveys along Breakspear Road South and Harvil Road, in the area shown on the map overleaf. This will help to inform our design decisions in the area.
We will capture 3-dimensional information on the drainage ditches and culverts in the area using a CCTV camera mounted on a small robot. Should we find a blockage, we may need to flush the drainage system using a high pressure water jet to carry out the investigation.
These surveys are taking place between 8pm and 5am to minimise impacts on the local road network. Temporary traffic management will be in place to ensure the surveys can be carried out safely and will be removed at the end of each shift.
Your utility services will not be affected.
Survey duration
– Breakspear Road South from 12 to 16 July
– Harvil Road from 26 to 30 July
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]