Notice of road closure, Ellesborough Road, Wendover

Work item: HS2-EKFB-26-2282

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Wendover
Worksite Name
Ellesborough Road
Contractor
EKFB JV
Type of works
Road closure, Vegetation trimming
Estimated Start Date
20/07/2026
Estimated End Date
21/07/2026

What we are doing

We will be cutting back overgrown vegetation, including hedges and weeds. This is to enable the installation of a low voltage cable on Ellesborough Road as part of the reinstatement of the road.

A water pressure test will also be carried out on the existing Ellesborough Road.

Location
Ellesborough Road, Wendover, Buckinghamshire

Duration
Monday 20 July (8:30am – 5:30pm)

Contingency: Tuesday 21 July (8:30am – 5:30pm)

What to expect

  • Day time closure of Ellesborough Road over two days.
  • A diversion route to be signposted.
  • Some noise from the works is expected.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]