Work Item Summary
- Project Phase
- Phase 1
- Region
- Oxfordshire
- Location
- Chipping Warden
- Worksite Name
- Culworth road
- Contractor
- EKFB JV
- Type of works
- Night-time working, Utility Works
- Estimated Start Date
- 02/11/2026
- Estimated End Date
- 02/11/2026
What we are doing
Openreach will be working in the area overnight installing the new telecommunications cables within the chambers built by EKFB in the recent utility works on Culworth Road.
Location
Blackgrounds Farm driveway and near the Barns, Culworth Road, Chipping Warden
Duration
Overnight working on Monday 2 November 2026
What to expect
- Localised low levels of noise and lighting.
- Residents access will be maintained.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.