Notice of road closure, Church Lane and Featherbed Lane Mixbury – April update

Work item: HS2-EKFB-26-1910

Work Item Summary

Project Phase
Phase 1
Region
Oxfordshire
Location
Mixbury
Worksite Name
Church Lane, Featherbed Lane
Contractor
EKFB JV
Type of works
Road closure, Road realignment, Utility Works
Estimated Start Date
14/05/2026
Estimated End Date
03/07/2026

What we are doing

Featherbed Lane Overbridge Realignment: The original 47-day road closure was planned to complete all works, including gas connections. However, due to delays in the delivery of bespoke parts, the gas connection works will now require an additional two-week closure.

While we have adjusted the start date to ensure the new highway opens on 15 June as scheduled, the road may need to remain closed for two weeks afterward to complete these connections. We will keep the community updated as plans are confirmed.

Location
Church Lane junction and Featherbed Lane, Mixbury.

Duration

Road closure
14 May to 15 June 2026.

Updated: 30 April

What to expect
A full road closure will be in place 24/7, with a diversion route available. Please allow extra time for your journey. Please also note that these works are subject to the necessary consents.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]