Notice of road closure, Marsh Lane, Aylesbury

Work item: HS2-MW-EK-Ph1-Ar-Ce-C2-UT-34-14/10/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Stoke Mandeville
Contractor
EKFB JV
Type of works
Road closure
Estimated Start Date
04/11/2021
Estimated End Date
05/11/2021

What we are doing

What are we doing?
As the project progresses, it is necessary to remove vegetation to enable future works to continue and to allow access to areas of the site.
In order to carry out essential surveys, we will be completing remaining vegetation clearance works near Marsh Lane.
We are required to close a section of the road near the level crossing for the duration of the works. This is for the safety of road users and our staff.
When will these works take place?
We will be working in the area from Thursday 4 November to Friday 5 November, from 9.30am to 3.00pm.
There will be a fully signed route diversion in place. We will work to open the roads to reduce disruption as soon as possible.
Works will take place between 8am and 6pm – Monday to Friday. Some additional weekend work may also take place.