Notice of road closure on Cotswold Way and Brackley Lane, Calvert Green
Work item: HS2-EKFB-26-2695
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Calvert
- Worksite Name
- Brackley Lane, Cotswold Way
- Contractor
- EKFB JV
- Type of works
- Road closure
- Estimated Start Date
- 09/11/2026
- Estimated End Date
- 20/12/2026
What we are doing
Reinstatement of the original road layout following the closure of the temporary Calvert link road. Works include; resurfacing, white lining, kerb installation, footpath extension, island construction and bollard installation.
Location
Cotswold Way/Brackley Lane junction, Calvert Green
Duration
Road closure from 23 November until 20 December 2026. Monday to Friday, 8am to 4pm.
What to expect
- A section of the road will be temporarily closed to safely complete these works.
- Access through the closure will be permitted for the morning and afternoon school bus service. Public bus services will be diverted, with revised timetable information to be provided by the operator.
- Access for residents within the closure area will be maintained at all times during the works.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]