Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Worksite Name
- West Ruislip Portal site
- Contractor
- SCS JV
- Type of works
- Sheet piling
- Estimated Start Date
- 22/06/2026
- Estimated End Date
- 29/08/2026
What we are doing
From 22 June to 29 August 2026 we will carry out sheet piling works within our West Ruislip Portal site, north of the Network Rail line and south of the Ruislip Golf Course. We will work during core hours, 9am to 6pm Mondays to Fridays and 9am to 1pm Saturdays.
We will monitor increased noise levels during the piling installation activities. We apologise for any disruption this may cause.
After the sheet pile installation works, we will continue with the following activities that are part of the Ickenham Stream diversion:
- Excavation works (July 2026)
- Drainage and reinforced concrete works (August 2026)
- Pipework installation (September 2026)
- Backfilling and sheet pile removal (October 2026)
- Shaft construction (November 2026)
We will keep you updated as the work progresses.