View In Your Area map
Notice of traffic management – Coleshill Heath Road
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Traf-6-15/09/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull, West Midlands
- Location
- Chelmsley Wood
- Worksite Name
- Coleshill Heath Road
- Contractor
- BBV JV
- Type of works
- Traffic management
- Estimated Start Date
- 18/10/2021
- Estimated End Date
- 19/11/2021
What we are doing
Construction of site entrance – Coleshill Heath Road
From Monday 18 October we will be constructing a new site entrance for our site compound at Heath Park off Coleshill Heath Road. To carry out these works safely, we will implement a three-way traffic light system on Coleshill Heath Road and Yorkminster Drive. The traffic lights will be in place until 19 November, 24 hours a day but will be manually controlled at peak times. The pedestrian access will be maintained at all times and the bus stop will be relocated outside the lane closure.