Skip to main page content
View route map

Old Oak Common Concrete Works

Work item: HS2-OOC - SCP-26-1743

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Cement pours, Construction
Estimated Start Date
19/09/2022
Estimated End Date
31/07/2026

What we are doing

Concrete works in the underground High Speed Station Box of Old Oak Common are continuing following the completion of excavation back in June 2024. Concrete pours are taking place on-site, with some pre-cast elements being delivered. This is to construct the walls, platforms, cores, and other elements of the future HS2 station and of the public realm. This will take place until July 2026.

Other concrete works include works on the Conventional Station notified in the AWN: Update on Old Oak Common Conventional Station Works (ref: HS2-OOC – SCP-26-1734) Oversized deliveries of pre-cast concrete elements will occasionally arrive in the early mornings before 8am onto site in order to limit impacts on local traffic. We will monitor and mitigate noise and dust coming from the concrete works.

Please see the link below for further information.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]