Old Oak Common Lane Bridge demolition September 2026

Work item: HS2-OOC - SCP-26-2493

Work Item Summary

Project Phase
Phase 1
Region
Old Oak and North Acton
Location
Old Oak Common lane
Worksite Name
Old Oak Common
Contractor
BBVS JV
Type of works
Bridge demolition, Lane closure
Estimated Start Date
21/09/2026
Estimated End Date
02/11/2026

What we are doing

We need to identify existing utilities in the ground so that we can excavate and build new bridge  foundations. We will remove the supporting walls (called ‘abutments’) of the former Wycombe line bridge between our site and the remaining bridge on Old Oak Common Lane. The walls of the old bridges on the east side of Old Oak Common Lane were demolished in April 2026.
There will be a single northbound lane closure on Old Oak Common Lane. Two-way traffic will be controlled by temporary traffic lights with full access to Wells House Road from both directions.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]