Overnight closure of A404 westbound at Amersham

Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-works-15-23/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Amersham
Worksite Name
A404 Amersham
Contractor
Align JV
Type of works
Road closure
Estimated Start Date
04/11/2021
Estimated End Date
05/11/2021

What we are doing

We need to safely remove the temporary safety barrier that borders the ventilation shaft site at Amersham. This will mean closing the A404 westbound (towards High Wycombe) at the junction with Whielden Lane. To minimise disruption, we will do this overnight from 10pm Thursday 4 November to 5am Friday 5 November. A local diversion route for traffic heading westbound will be in place, using the A404, A4010 and A413.