Pedestrian gate installation for site accommodation

Work item: HS2-BCZ – SCP-26-2081

Work Item Summary

Project Phase
Phase 1
Region
Birmingham
Location
Curzon Street
Contractor
Mace Dragados JV
Type of works
Pedestrian gate installation
Estimated Start Date
21/05/2026
Estimated End Date
08/06/2026

What we are doing

Location 

Curzon Street  

Duration 

Thursday 21 May to Monday 8 June which may include some Saturday working   

What we are doing 

Installing a new set of double pedestrian gates to facilitate access to the new site accommodation. Which will be located to the right of the Woodman Pub by the seating area, which will remain open.   

What to expect 

We will need to partly close the footpath to safely install the new gate. We will put temporary barriers in place to maintain safety. We will not dismantle the existing hoarding is taking place.  

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]