Skip to main page content
View route map

Update: Piling in Euston Throat, Camden – 30 November to spring 2027

Work item: HS2-SCS-26-2753

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Euston Approaches, Euston Throat
Contractor
SCS JV
Type of works
Piling work
Estimated Start Date
30/11/2026
Estimated End Date
31/03/2027

What we are doing

We previously informed you that we would start installing piles within our Euston Throat site from 16 November. We will now start these works from Monday 30 November and aim to complete them by spring 2027. Our working hours are Monday to Friday, 8am to 6pm. However, the concrete pour for each pile must be completed within a single shift so the concrete does not dry out. This means we will sometimes need to work until 10pm to finish a pile. We’ll work over four weekends to complete four piles between January and March 2027.

To access the area safely, we will need to install these piles when the tracks are not in use. We will provide updates when we have confirmed dates and working hours for these works.

We install a pile by drilling a hole in the ground and then filling the hole with concrete and steel. Once we finish pouring concrete, we use a vacuum excavator to remove any excess concrete before leaving the pile to set. This is the quietest possible method of installing piles. However, you may notice increased noise from the piling rig, excavator, and vacuum excavator as we drill and remove muck and concrete. You may also notice some vibration from the piling.

We’ll monitor our works closely to ensure we are operating within approved noise and vibration limits.

For more information about piling works, including how piles are installed and what to expect during construction, please visit our piling fact sheet here.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]