Skip to main page content
View route map

Postcard invite for Euston Approaches rooftop visit and Community Hub drop in event

Work item: HS2-SCS-26-2473

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Euston Approaches, Euston Community Hub
Contractor
SCS JV
Type of works
Community Event, Drop ins
Estimated Start Date
22/09/2026
Estimated End Date
30/09/2026

What we are doing

Postcard invite for Euston Approaches roof visit and Community Hub drop in event

Please join us at Euston community hub for an in-person drop in event on Tuesday 22 September from 4:30pm to 7pm.

Here you’ll be able to learn more about HS2 works in Camden. We’ll provide updates and answer questions on:

• Works at Euston Approaches and Euston Station sites
• The Euston tunnel, and
• Remobilisation at the Adelaide Road Vent Shaft site

This event will be at the Community Hub, North Gower Street, London NW1 2LYNorth Gower Street, London NW1 2LY

Rooftop guided tour at Euston Approaches site

We would like to invite you to a rooftop guided tour at our Euston Approaches worksite on Wednesday 30 September, between 5:30pm and 6:30pm at Stephenson House, NW1 1SJ (entrance on Harrington Street).

At this event you will be able to:

• Join us for a bird’s eye view of HS2 works in Euston Approaches
• See what we are building
• Ask questions about our works

Places are limited to keep groups small. To apply for a place on the rooftop tour, please register with Eventbrite using the QR code by following the link below:

Rooftop Guided Tour registration

We look forward to seeing you.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]