Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- West Ruislip
- Worksite Name
- West Ruislip Portal site
- Contractor
- SCS JV
- Type of works
- Sheet piling
- Estimated Start Date
- 16/12/2026
- Estimated End Date
- 22/12/2026
What we are doing
We’ll install sheet piles to prepare the ground for the permanent access road and we’ll remove sheet piles around underground water tanks.
We’ll use piling equipment, a crane to lift materials, excavators and generators.
Duration
16 November to 22 December 2026 8am to 6pm Monday to Friday, 8am to 1pm Saturday
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.