Skip to main page content
View route map

Temporary lane closures along sections of the A452 northbound and A446 southbound near Northway Island from Wednesday 2 June to Friday 4 June 2021

Work item: HS2-EW-LM-Ph1-Ar-No-N1-Traf-8-05/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Solihull, Warwickshire, West Midlands
Location
Bickenhill, Coleshill
Contractor
LM JV
Type of works
Traffic management, Vegetation clearance
Estimated Start Date
02/06/2021
Estimated End Date
04/06/2021

What we are doing

Subject to obtaining the relevant consents, from Wednesday 2 June to Friday 4 June, 9.30am to 3.30pm each day, temporary lane closures will be installed along sections of the A452 northbound and A446 southbound near Northway Island. We are carrying out these traffic measures to allow safe access to our work sites to prepare for future construction works, which includes roadside vegetation clearance.

Our works start date and duration may change because our works are dependent on the relevant consents being granted, which may affect when we carry out our planned traffic measures. We’ll inform you of any changes to these planned traffic measures before they take effect, if required, at:  www.hs2insolihull.co.uk

These traffic measures will be carried out in conjunction with a new direction of travel for road users around Northway Island, which will commence on Monday 24 May.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]