Temporary traffic management and lane closure, Harvil Road, Hillingdon
Work item: HS2-ALIGN-25-1390
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hillingdon
- Location
- Hillingdon
- Worksite Name
- Harvil Road
- Contractor
- Align JV
- Type of works
- Lane closure, Traffic management
- Estimated Start Date
- 03/06/2026
- Estimated End Date
- 23/06/2026
What we are doing
We are removing the construction bellmouth at the junction of Dews Lane and resurfacing the bellmouth. A single lane closure and three-way traffic signals on Harvil Road will be put in place for the duration of these works.
Location
Dews Lane junction with Harvil Road, London Borough of Hillingdon.
Duration
A single lane closure will be in place from Wednesday 3 June to Tuesday 23 June 2026 9:30am to 3pm.
What to expect
- Traffic management will be in place 9:30am to 3pm each day for the duration of these works to control traffic and ensure that operatives can work safely in the carriageway.
- Please allow additional time for your journey during these works.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.