Thamews Water works on The Greenway, 27 to 29 March

Work item: HS2-MW-TW-Ph1-Ar-So-S1-Prog-works-1-18/10/2022 -2

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon, London
Location
The Greenway
Contractor
Thames Water
Type of works
Utility works / surveys
Estimated Start Date
27/03/2023
Estimated End Date
29/03/2023

What we are doing

Thames Water need to return to the manhole on The Greenway to carry out our final piece of work outside no 43. We will be pouring more concrete into the manhole, the same as we did earlier this month. We will be using a pump on Monday 27 March. The vehicle carrying concrete will again need to reverse up part of the road and will have two banksmen directing it at all times, it will give way to other vehicles.

The road will remain open at all times, but as before it will be reduced to one lane for a short distance – give way signs will be in place. On road parking will be restricted in the immediate area but residents will be able to access their driveways at all times. Footpaths on both sides of the road will remain open.

We will reinstate the road on Tuesday 28 and Wednesday 29 March.