24/7 track-level works in Camden Cutting during the summer railway closure

Work item: Reference no: HS2-EW-SCS-Ph1-Ca-S1-Prog-works-40-04/09/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Camden
Contractor
SCS JV
Type of works
Construction, Utility works / surveys
Estimated Start Date
22/04/2021
Estimated End Date
31/08/2021

Work item details

Works to rail bridges – May to September 2021

In addition to the works happening as part of the spring rail closure (Notification – 24/7 works during rail closures), we are continuing with weekend overnight works at track level.  These works include surveys to Mornington Street bridge and strengthening works to a rail bridge at track level.

Summer rail closure – 17 July to 31 August

During the summer rail closure, we will install ground anchors, structural steelwork and bridge supports beneath the rail bridge at track level. We will carry out these works 24/7 – weekdays and weekends.  Follow the link below for further details.

Download information relating to these works