Traffic management and night closure of Moorhall Road, Hillingdon

Work item: HS2-ALIGN-26-2204

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
Harefield, Hillingdon
Worksite Name
Moorhall Road
Contractor
Align JV
Type of works
Overnight road closure, Traffic management
Estimated Start Date
29/06/2026
Estimated End Date
31/07/2026

What we are doing

We will be removing the temporary construction bellmouth and resurfacing the road where the Colne Valley Viaduct crosses Moorhall Road.

Location
Moorhall Road, Harefield, Hillingdon.

Duration
Phase 1 contraflow system will be in place from 29 June to 27 July.

Phase 2 overnight road closure will take place from 27 July to 31 July from 10pm to 5am every night.

What to expect
Temporary traffic signs, cones and barriers will be in place to guide you safely around the work zones for the safety of both drivers and our workforce. While these schedules are designed to avoid peak commuting hours, we recommend allowing extra time for your journeys and watching out for temporary changes.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.