Traffic management Wood End Lane, Fradley

Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Traf-29-10/11/2021 JW

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire, West Midlands
Location
Lichfield
Worksite Name
Wood End Lane
Contractor
BBV JV
Type of works
Road closure, Traffic management
Estimated Start Date
25/10/2021
Estimated End Date
12/11/2021

What we are doing

We will be creating a new site entrance to our compound and haul road. This work will include preparation of the road edges and laying of new kerb stones. We will also be carrying out utility trial trenching, along Wood End Lane, which will involve digging into the ground to establish what is underneath the surface. This will provide us with information on the location of underground utilities, which we need to assess as we develop our construction plans.

These works will take place from 25 October – 11 November

Our working hours will be:

• Daytime: 8:00am to 6:00pm for the access road construction, a lane closure with temporary traffic lights on Wood End Lane and Netherstowe Lane.

• Overnight: 8:00pm to 6:00am for the survey works, this is a road closure of Wood End Lane with a diversion.

Our workforce can be on site one hour before and after to set up and take our work equipment.
There will be no weekend working. Businesses will be open as usual.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]