Update- Extension of Hunningham Road, Offchurch closure
Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Traf-45-14/06/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Offchurch
- Worksite Name
- Hunningham Road
- Contractor
- BBV JV
- Type of works
- Road closure, Traffic management
- Estimated Start Date
- 12/07/2021
- Estimated End Date
- 13/08/2021
What we are doing
To enable BT to complete their works on unknown utility cables we now need to extend the working period to the 13 August from the original end date of 30 July. Please accept our apologies for the delay and we will endeavour to complete these works quickly as possible.
We will be creating a controlled crossing on Hunningham Road. The crossing will allow us to safely move our construction plant across the road as we undertake various earthworks in the area.
To allow us to construct this crossing the road will be closed from 12 July to 13 August. Please note that Hunningham Road will be closed on a 24/7 basis including weekends while these works are being carried out. Access will be maintained to all properties on Hunningham Road throughout this period.