Update: further ground investigations on Chase Road
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-works-1-23/07/21
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Old Oak
- Worksite Name
- Old Oak Common
- Contractor
- SCS JV
- Type of works
- Ground investigations
- Estimated Start Date
- 09/08/2021
- Estimated End Date
- 10/09/2021
What we are doing
Ground investigation trial holes on Chase Road
We previously notified you in April 2021 about ground investigation works on Chase Road. The ground investigation works will continue until 10 September 2021. The works will be carried out in phases lasting between two and five days each. Maps showing the phases of the works are included on the following pages.
During each phase, we’ll excavate a trial hole to confirm the location of utilities under the road surface. This will help to inform the design of future works to build the HS2 tunnels and crossover box.
Traffic management will be in place during these works, including the suspension of some parking bays along Chase Road and Gorst Road. This is to ensure the safety of our staff and pedestrians. Vehicles will be able to travel on Chase Road during these works.
Bus stops PD, PJ and W on Chase Road will be temporarily suspended during some phases of these works. We apologise for any inconvenience this may cause. We will use noise reducing barriers where possible, to help minimize any noise disruption to you and dampen down any activities that may cause dust production.
The dates for these works may change.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]