UPDATE Notice of Public Right of Way closure, Radstone August 2026

Work item: HS2-EKFB-26-2399

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Radstone
Worksite Name
PRoW AX18
Contractor
EKFB JV
Type of works
Footpath closures
Estimated Start Date
02/02/2025
Estimated End Date
30/09/2026

What we are doing

We are temporarily closing the bridleway to complete the final tie-in and realignment work for the new AX18 bridleway accommodation bridge.

Once this work is complete, the bridleway will reopen on its new, permanent alignment, including safe access over the new bridge.

Location
Bridleway AX18, located near Radstone Road in Radstone, with its location detailed on the map on page 2.

Duration – Until 1 September 2026

What to expect
Full closure 24/7 with a diversion till 19 August 2026 and then no diversion.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.