Update of works at Atlas Road roundabout in Victoria Road
Work item: HS2-EW-CSJV-Ph1-OOC-St-S4-UT-11-07/05/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak
- Contractor
- CS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 13/05/2021
- Estimated End Date
- 17/05/2021
What we are doing
We are sorry these works have been delayed and apologise for extending the four-way traffic management on the Atlas Road roundabout to 17 May 2021. Once we are suitably clear of the Atlas Road roundabout, we will remove the current four-way traffic management and install two-way traffic management on Victoria Road.