Update of works at Canterbury Works site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-16/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Canterbury Road
- Worksite Name
- Canterbury Works
- Contractor
- SCS JV
- Type of works
- Piling
- Estimated Start Date
- 01/09/2021
- Estimated End Date
- 19/11/2021
What we are doing
Update to site piling works
We notified you in late July 2021 about our ongoing piling works at the Canterbury Works site. We had planned to carry out our final piling works along our boundary with Network Rail from 2 to 9 August 2021. Unfortunately, these works could not take place as planned and have now been rescheduled to take place from 1 September 2021 for approximately two weeks.
We will be working between 8am and 6pm Monday to Friday and 9am and 1pm on Saturdays if required. The location of these works can be found on page 2.
The dates may change. We will keep you updated via www.hs2.org.uk/in-your-area/map
Our piling method
We used a press piling unit to push in the piles along the boundary with the school during the first phase of piling. To protect the nearby Network Rail tracks and trains, our piling method will change for the phase along the Network Rail boundary to a vibration hammer rig.
During these piling works you may experience some additional noise and vibration. We will be carrying out vibration and noise monitoring to ensure that any disruption is kept to a minimum.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]