Update on closure of Tilehouse Lane, West Hyde
Work item: HS2-EW-Align-Ph1-Ar-Ce-C2-Prog-works-4-19/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Hertfordshire
- Location
- West Hyde
- Contractor
- Align JV
- Type of works
- Road closure
- Estimated Start Date
- 31/08/2021
- Estimated End Date
- 31/08/2022
What we are doing
Extended closure of Tilehouse Lane to allow us to build a new permanent diversion route over the HS2 railway, access will be maintained at all times. Also minor vegetation clearance and carrying out essential drainage maintenance works along the A412 from 20 September 2021 to 01 October 2021 where 2 way traffic management will be operational.