Update on works inside Northolt Tunnel

Work item: HS2-SCS-26-1755

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Hillingdon
Contractor
SCS JV
Type of works
Concrete break out, Construction
Estimated Start Date
02/09/2025
Estimated End Date
30/11/2026

What we are doing

Construction of the 8.4 mile (13.5km) long twin-bore Northolt Tunnel is complete between Old Oak Common and West Ruislip.

We are continuing with building the emergency and maintenance walkways inside the tunnel , with works ongoing until autumn 2026. These walkways will allow passengers to safely evacuate a train and walk to the nearest cross passage and rescue train should there be an emergency.

The cross passages are short tunnels which connect two parallel running tunnels approximately 500 metres apart along the Northolt tunnel route. The next phase of works will be to install the cross passage doors which will provide fire protection between the cross passages, these works are expected to be completed by late autumn 2026.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]