Update on utility works in Drummond Street
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-28-28/03/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden, London
- Location
- Camden, Euston station
- Contractor
- CS JV
- Type of works
- Early construction works, Utility works / surveys
- Estimated Start Date
- 01/01/2021
- Estimated End Date
- 31/05/2021
What we are doing
Since January 2021, we have been carrying out a series of utility works on Drummond Street between Cobourg Street and North Gower Street. These include:
- BT Openreach chamber construction works, which are continuing in the eastern junction with North Gower Street until late May; and
- CSjv sewer construction and gas and water disconnection works, which started 22 March and will run until the end of May.
The PDF notification below includes more detail about the works and information about traffic diversions and refuse collections.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]