Work item: HS2-EW-SCS-Ph1-Ar-So-S1-UT-28-28/03/2021

Work Item Summary

Project Phase
Phase 1
Region
Camden, London
Location
Camden, Euston station
Contractor
CS JV
Type of works
Early construction works, Utility works / surveys
Estimated Start Date
01/01/2021
Estimated End Date
31/05/2021

What we are doing

Since January 2021, we have been carrying out a series of utility works on Drummond Street between Cobourg Street and North Gower Street. These include:

  • BT Openreach chamber construction works, which are continuing in the eastern junction with North Gower Street until late May; and
  • CSjv sewer construction and gas and water disconnection works, which started 22 March and will run until the end of May.

The PDF notification below includes more detail about the works and information about traffic diversions and refuse collections.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]