Update: Overnight Central Line bridge work – October 2026
Work item: HS2-OOC - SCP-26-2078
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Excavation works, Overnight works
- Estimated Start Date
- 14/06/2026
- Estimated End Date
- 12/11/2026
What we are doing
We are continuing with our work to support the construction of railway bridges near the Central Line, around 90 metres south from the rear of properties on Wells House Road.
For this we need to install a temporary wall to support the pouring of the concrete. The work will involve some drilling and fixing, and some machinery operating to lift in the temporary wall. We will be using a crane situated within site to lift sections of the temporary wall into position near the bridge. As we are lifting towards and next to the railway, for safety reasons we need to carry out these works overnight whilst the Central Line is not operating. We have been continually updating this notification as works have progressed.
Working times
- Sunday 18 October and Thursday 22 October: Install temporary works
- Sunday 25 October – Thursday 29 October: Install temporary works
- Sunday 1 November – Thursday 5 November: Install temporary works
- Sunday 9 November – Thursday 12 November: Install temporary works
All working hours are Sunday to Thursday within 10pm – 6am
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]