Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Central Line near South of Wells House Road
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Overnight weekend working, Overnight works
- Estimated Start Date
- 22/11/2026
- Estimated End Date
- 03/12/2026
What we are doing
This is an update to the previous AWN Overnight Central Line bridge work (ref: HS2 OOC – SCP-26-2078). We have to carry out overnight works , in order to prepare for the installation of the new bridge beams at Christmas . The works will involve task lighting and some noise and vibration. We will complete our activity as quickly as possible to reduce disruption.
We are continuing to construct a new railway bridge over the Central Line (around 90 metres south from the rear of properties on Wells House Road). Following the construction of the concrete bridge walls over the summer, we are now continuing with the installation of the drainage pipes. We will also be placing and compacting material to support the new bridge walls.
We have been continually updating this notification as works have progressed.
Working times and description of activity
- Sunday 22 November – Tuesday 24 November: Painting and drainage
- Tuesday 24 November – Thursday 26 November: Drainage and backfilling
- Sunday 29 November – Thursday 3 December: Drainage and backfilling
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.