Update: Utility works in South Hampstead, Camden

Work item: HS2-SCS-26-2475

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Alexandra Road, Finchley Road, Hilgrove Road
Contractor
SCS JV
Type of works
Bus Stop suspensions, Footpath closures, Lane closure, Utility Works
Estimated Start Date
01/12/2026
Estimated End Date
21/02/2027

What we are doing

We will be working in the locations below:

Finchley Road

We will close the northbound lane and bus lane, close to the Gym Group. There will be no left turn northbound onto Hilgrove Road from Finchley Road. Bus stops L, M and N will be suspended. The nearest alternative is bus stop A on Finchley Road.

Hilgrove Road

We will close the westbound lane. There will be no vehicle access to Alexandra Road from Hilgrove Road.

Alexandra Road
We will have a partial road closure at the top of Alexandra Road at the junction with Hilgrove Road. Vehicles will only be able to access from Loudoun Road. The entrance to Dorman Way will remain open. 

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.