Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Hampstead Road, Robert Street
- Contractor
- SCS JV
- Type of works
- Footpath closures, Lane closure, temporary traffic lights
- Estimated Start Date
- 26/10/2026
- Estimated End Date
- 04/12/2026
What we are doing
We previously informed you that we have closed Robert Street, the southbound lane of Hampstead Road south of Cardington Street and the pedestrian crossing south of Robert Street. We have installed a temporary crossing to divert pedestrians to the northbound footpath. Access to Regent’s Park will be via Varndell Street. Access to Hampstead Road will be via William Road for southbound traffic and via Varndell Street for northbound traffic
We had planned to finish these works on 20 November 2026, but due to delays, we now expect to finish on 4 December 2026.
After 4 December, we’ll continue with these works in the northbound lane and footpath on Hampstead Road. We’ll also carry out trial holes in this location. We will update you when we have confirmed the dates. We apologise for the inconvenience this work may cause.
HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]