Update on utility connection works in Euston Approaches – 27 July to 18 September 2026

Work item: HS2-SCS-26-2443

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Park Village East, Stanhope Street
Worksite Name
Euston Approaches
Contractor
SCS JV
Type of works
Utility Works
Estimated Start Date
27/07/2026
Estimated End Date
18/09/2026

What we are doing

We have been diverting utility services on and next to Hampstead Road before we begin works to extend Hampstead Road bridge.

As part of these works, we previously installed new cable routes from Lidlington Place to Varndell Street via Granby Terrace to replace the existing route on Hampstead Road.

In the next stage of our works, we will install an additional section of ducting and connect the new cable routes before the existing services are transferred.

Utility connection works in corner of Park Village East and Stanhope Street – Ongoing to 18 September

Since 27 July, UK Power Networks (UKPN) have been carrying out jointing works on Stanhope Street and Park Village East. Whilst UKPN are working in this area, we’ll also excavate the area and install additional ducting.

We previously informed you we expect these works to finish on 21 August, however UKPN have also informed us of additional utility diversion works in this area. We have decided to carry out these additional works whilst the traffic management is in place and parking bays are suspended, rather than returning at a later date. We expect these works to finish on 18 September.

During this period, parking bay suspensions will be in place on both Stanhope Street and Park Village East, and temporary traffic lights will be used to manage vehicle flow through the works area. Working hours will be Monday to Friday, 8:00am to 6:00pm. If the work takes longer than anticipated, daytime work may also be required on some weekends to complete the works safely.

There may be some noise during jointing works. These works will be monitored closely to ensure they remain within the noise limits agreed with the local council.

We apologise for any inconvenience these works may cause.

HS2 is undergoing a comprehensive reset to ensure it can be built efficiently and for the lowest reasonable cost. This work is being carried out in stages and will be completed in 2026. We will provide you with updates on the reset and what this means for our plans to build the railway in your area.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]